Project Budget

The project budget has undergone several revisions.

Initial Budget, March 10, 2005

Cob Bench
Clay$120.00
Sand$80.00
Straw$60.00
Heat conduit$120.00
Mortar$40.00
Finish Stones$1,200.00
$1,620.00
Dialogue Dome
Clay$90.00
Sand$60.00
Straw$50.00
Heat conduit$20.00
Mortar$20.00
Root Barrier$400.00
Waterproof Liner$400.00
Flashing$80.00
Drainage System$400.00
Nails$25.00
Screws$35.00
Lag Bolts$35.00
Hurricane Clips$35.00
Joist Hangers$70.00
$1,720.00
Cob Oven
Rebar$80.00
Clay$90.00
Sand$60.00
Straw$50.00
Heat conduit$20.00
Mortar$20.00
Finish Stones$800.00
$1,120.00
Cob Bench
Clay$120.00
Sand$80.00
Straw$60.00
Heat conduit$120.00
Mortar$40.00
Finish Stones$1,200.00
$1,620.00
Spiral Foundation
Cutting$1,200.00
Finish Stones$3,000.00
Etching$5,000.00
Sand$30.00
Mortar$80.00
$9,310.00
Landscaping
Grasses$140.00
Herbs$60.00
Rushes$100.00
Rocks$200.00
Mulch$10.00
$510.00
Consultation
Natural builder$2,000.00
Assistant$1,500.00
Site Liasions$1,000.00
$4,500.00
Misc Costs
Transportation$70.00
Total$20,470.00
10% Cost Overrun$2,047.00

Grand Total

$22,517.00

Budget Revision, March 25, 2005

Cob Bench
Clay$120.00
Sand$80.00
Straw$60.00
Heat conduit$120.00
Mortar$40.00
Finish Stones$1,200.00
$420.00
Dialogue Dome
Clay$90.00
Sand$60.00
Straw$50.00
Heat conduit$20.00
Mortar$20.00
Root Barrier$400.00
Waterproof Liner$400.00
Flashing$80.00
Drainage System$400.00
Nails$25.00
Screws$35.00
Lag Bolts$35.00
Hurricane Clips$35.00
Joist Hangers$70.00
$1,720.00
Cob Oven
Rebar$80.00
Clay$90.00
Sand$60.00
Straw$50.00
Heat conduit$20.00
Mortar$20.00
Finish Stones$800.00
$320.00
Cob Bench
Clay$120.00
Sand$80.00
Straw$60.00
Heat conduit$120.00
Mortar$40.00
Finish Stones$1,200.00
$420.00
Spiral Foundation
Cutting$1,200.00
Finish Stones$3,000.00
Etching$5,000.00
Sand$30.00
Mortar$80.00
$9,310.00
Landscaping
Grasses$140.00
Herbs$60.00
Rushes$100.00
Rocks$200.00
Mulch$10.00
$510.00
Consultation
Natural builders$4,500.00
Assistant$1,000.00
Site Liasions$1,000.00
$6,500.00
Misc Costs
Transportation$70.00
10% Cost Overrun$2,047.00

Finishing Phase Total$14,557

VBC Development Total

$9,960

Budget, version 3, April 12, 2005


Here is the revisited budget:


>
> 2 cob benches @ $500 = $1000
> Dialogue Dome = $3000
> Smaller dome over oven = $1000
> Cob oven = $750
> Landscaping = $500
> Construction labor = $4500 (no Assistant and Site Liaisons)
> Misc. + overrun = $1000
>

Total Construction Cost = $11,750


>
> I determined these material costs by using many of the same detailed numbers
> listed in the March 25 budget, but I eliminated the expensive finish stone
> and made some other minor adjustments based largely on my intuition of
> reasonable costs.
>

These costs can be covered by the following revenue:


>
> Donated materials = $700
> City Repair allocation = $3500
> OSD Grant = $7000
> PSU fund raising or grant = $550
>

Total Revenue = $11,750


>
> Notice I'm proposing that the PSUrth students raise $550 somehow.
>

Now, the total project budget would actually have to include matching in-kind
> services as per my email attachment to OSD (April 6, 2005), as follows:



> in-kind design services = $9600
> in-kind PSU staff time = $480
>

total in-kind services = $10,080


>

So, the total project budget is $11,750 (construction costs) + 10,080 (design services, etc.) = $21,830.