Project Budget
The project budget has undergone several revisions.
Initial Budget, March 10, 2005
| Cob Bench |
| Clay | $120.00 |
| Sand | $80.00 |
| Straw | $60.00 |
| Heat conduit | $120.00 |
| Mortar | $40.00 |
| Finish Stones | $1,200.00 |
| $1,620.00 |
| Dialogue Dome |
| Clay | $90.00 |
| Sand | $60.00 |
| Straw | $50.00 |
| Heat conduit | $20.00 |
| Mortar | $20.00 |
| Root Barrier | $400.00 |
| Waterproof Liner | $400.00 |
| Flashing | $80.00 |
| Drainage System | $400.00 |
| Nails | $25.00 |
| Screws | $35.00 |
| Lag Bolts | $35.00 |
| Hurricane Clips | $35.00 |
| Joist Hangers | $70.00 |
| $1,720.00 |
| Cob Oven |
| Rebar | $80.00 |
| Clay | $90.00 |
| Sand | $60.00 |
| Straw | $50.00 |
| Heat conduit | $20.00 |
| Mortar | $20.00 |
| Finish Stones | $800.00 |
| $1,120.00 |
|
| Cob Bench |
| Clay | $120.00 |
| Sand | $80.00 |
| Straw | $60.00 |
| Heat conduit | $120.00 |
| Mortar | $40.00 |
| Finish Stones | $1,200.00 |
| $1,620.00 |
| Spiral Foundation
| | Cutting | $1,200.00 |
| Finish Stones | $3,000.00 |
| Etching | $5,000.00 |
| Sand | $30.00 |
| Mortar | $80.00 |
| $9,310.00 |
| Landscaping |
| Grasses | $140.00 |
| Herbs | $60.00 |
| Rushes | $100.00 |
| Rocks | $200.00 |
| Mulch | $10.00 |
| $510.00 |
| Consultation
| | Natural builder | $2,000.00 |
| Assistant | $1,500.00 |
| Site Liasions | $1,000.00 |
| $4,500.00 |
| Misc Costs |
| Transportation | $70.00 |
|
| Total | $20,470.00 |
| 10% Cost Overrun | $2,047.00 |
Grand Total | $22,517.00 |
Budget Revision, March 25, 2005
| Cob Bench |
| Clay | $120.00 |
| Sand | $80.00 |
| Straw | $60.00 |
| Heat conduit | $120.00 |
| Mortar | $40.00 |
| Finish Stones | $1,200.00 |
| $420.00 |
| Dialogue Dome |
| Clay | $90.00 |
| Sand | $60.00 |
| Straw | $50.00 |
| Heat conduit | $20.00 |
| Mortar | $20.00 |
| Root Barrier | $400.00 |
| Waterproof Liner | $400.00 |
| Flashing | $80.00 |
| Drainage System | $400.00 |
| Nails | $25.00 |
| Screws | $35.00 |
| Lag Bolts | $35.00 |
| Hurricane Clips | $35.00 |
| Joist Hangers | $70.00 |
| $1,720.00 |
| Cob Oven |
| Rebar | $80.00 |
| Clay | $90.00 |
| Sand | $60.00 |
| Straw | $50.00 |
| Heat conduit | $20.00 |
| Mortar | $20.00 |
| Finish Stones | $800.00 |
| $320.00 |
|
| Cob Bench |
| Clay | $120.00 |
| Sand | $80.00 |
| Straw | $60.00 |
| Heat conduit | $120.00 |
| Mortar | $40.00 |
| Finish Stones | $1,200.00 |
| $420.00 |
| Spiral Foundation
| | Cutting | $1,200.00 |
| Finish Stones | $3,000.00 |
| Etching | $5,000.00 |
| Sand | $30.00 |
| Mortar | $80.00 |
| $9,310.00 |
| Landscaping |
| Grasses | $140.00 |
| Herbs | $60.00 |
| Rushes | $100.00 |
| Rocks | $200.00 |
| Mulch | $10.00 |
| $510.00 |
| Consultation
| | Natural builders | $4,500.00 |
| Assistant | $1,000.00 |
| Site Liasions | $1,000.00 |
| $6,500.00 |
| Misc Costs |
| Transportation | $70.00 |
| 10% Cost Overrun | $2,047.00 |
|
| Finishing Phase Total | $14,557 |
VBC Development Total | $9,960 |
Budget, version 3, April 12, 2005
Here is the revisited budget:
>
> 2 cob benches @ $500 = $1000
> Dialogue Dome = $3000
> Smaller dome over oven = $1000
> Cob oven = $750
> Landscaping = $500
> Construction labor = $4500 (no Assistant and Site Liaisons)
> Misc. + overrun = $1000
>
Total Construction Cost = $11,750
>
> I determined these material costs by using many of the same detailed numbers
> listed in the March 25 budget, but I eliminated the expensive finish stone
> and made some other minor adjustments based largely on my intuition of
> reasonable costs.
>
These costs can be covered by the following revenue:
>
> Donated materials = $700
> City Repair allocation = $3500
> OSD Grant = $7000
> PSU fund raising or grant = $550
>
Total Revenue = $11,750
>
> Notice I'm proposing that the PSUrth students raise $550 somehow.
>
Now, the total project budget would actually have to include matching in-kind
> services as per my email attachment to OSD (April 6, 2005), as follows:
> in-kind design services = $9600
> in-kind PSU staff time = $480
>
total in-kind services = $10,080
>
So, the total project budget is $11,750 (construction costs) + 10,080 (design services, etc.) = $21,830.